New build snagging: the electrical checks to make before you accept the keys.
Electrical snags in a new build are common and usually cheap to fix if you report them early. Check the paperwork first, then work room by room, test every socket and light, and note anything that looks unfinished, so you can send the builder a clear list while they are still responsible.
Paperwork first
- An Electrical Installation Certificate for the installation, signed and complete.
- The Building Regulations completion paperwork from building control or a competent person scheme.
- Smoke and heat alarm information, and any commissioning sheets.
- Manuals for heating controls, ventilation and the consumer unit, if supplied.
- Your builder's warranty or defects process, so you know how to report faults. Many new homes come with a defects period; check the terms.
Room by room checklist
| Area | What to check |
|---|---|
| Every room | Each socket has power, switches are straight, plates are secure and not cracked. |
| Lights | Every light works from every switch, two-way switches work from both ends, dimmers dim. |
| Kitchen | Oven, hob, extractor and appliances are powered, isolators are accessible. |
| Bathrooms | Extractor runs, lights work, shaver sockets and pull cords operate. |
| Consumer unit | Labels are present and clear. Press the RCD test button and confirm it trips, then reset. |
| Smoke and CO alarms | Test buttons work, alarms interlink where fitted, no loose covers. |
| Outside | External lights, sockets and doorbell work. Covers are sealed. |
| Data and TV | Points are present where promised and connect to the right place. |
A simple socket tester
A plug-in socket tester shows whether a socket has power and that wires are in the right places. It does not replace proper testing and cannot prove the circuit is safe, but it can catch reversed wiring and dead sockets quickly. Do not open sockets, the consumer unit or any cover yourself.
Report in writing
Send the builder a dated list with photos and room names. Keep copies. If something looks unsafe, such as scorching, a buzzing socket or an RCD that will not reset, stop using it and report it as urgent.
When to bring in an independent electrician
If the builder's paperwork is missing, if you see signs of poor workmanship, or if you want reassurance on a large or high-value home, an independent inspection shows what the certificate says on paper matches what is behind the walls. It is also wise if you plan to add an EV charger, solar or a battery, because the consumer unit and supply need checking for spare capacity. See EV charger installation.
Common new build snags
- Missing or misplaced sockets compared with the plan.
- Switches wired the wrong way round, or two-way lights that fail from one end.
- Unlabelled consumer unit ways.
- Cracked faceplates, paint on accessories or loose fittings.
- Extractor fans that run but do not move air, or that are not connected to a switch.
- Smoke alarms that do not interlink or have no backup battery.
Margate new builds and conversions
Thanet has seen new homes and flat conversions, and buyers of converted properties in Cliftonville and Westbrook should also check older parts of the installation which may have been retained rather than replaced. Coastal conditions mean external fittings, meter boxes and doorbells on seafront properties should be sealed and made of suitable materials; our salt-air guide explains why. Check any shared services or communal alarm arrangements with the management company. If you want a second opinion on a new home, get in touch.
Doing a proper walkthrough
- Go round with a printed floor plan and mark each socket, switch and light on it.
- Test with everything off first, then with all lights on, to see whether the house holds up.
- Run appliances you plan to use, such as the oven and washing machine, to check the supply and isolators.
- Look at each faceplate close up for gaps, paint splashes, cracks and loose fixings.
- Check outside after dark so you can see whether the lights come on and cover the paths.
What should worry you
- A consumer unit that trips repeatedly or will not reset.
- Warm or discoloured faceplates, buzzing sounds or a burning smell.
- Exposed conductors, loose cables or missing cover plates.
- No test certificate, or one that does not match the property.
- Sockets that do not match the plan, particularly in kitchens and bedrooms.
Keep up the pressure politely
Builders deal with many homes at once, and a clear, dated list with photos is hard to ignore. Follow up in writing, note who you spoke to and when, and keep copies of every reply. Defects found in the first months are covered under your warranty or sales contract, so report them early. If a fault is unsafe, say so clearly and ask for an urgent visit.
Before you move in
Photograph the consumer unit, the meter and every room before furniture goes in, and write down the meter readings on the day you collect the keys. Check where the main isolator is and show everyone in the household how to find it. If the home has solar, a battery or an EV charger, ask for their handover documents and commissioning records, and find out who to call if they fail.
Common questions
What paperwork should I get with a new build?
An Electrical Installation Certificate, Building Regulations completion documentation, alarm commissioning details and manuals. Ask for anything missing before you accept the keys.
Can I test the RCD myself?
Yes, pressing the test button on the consumer unit is safe and expected. It should trip, and you reset it afterwards. Do not open the unit.
Who fixes electrical snags in a new build?
The builder is normally responsible during the defects period. Report faults in writing and keep records, and get an independent electrician if you are unsure.
Need this done on your property?
Photos, postcode and a short description to hello@margateelectrical.co.uk or WhatsApp 07763 100 477. Same-day fixed quote.