Service · Solar + battery
Solar PV and battery systems across Margate CT9. MCS-certified installer route, DNO G98/G99 notification handled, honest Thanet-generation numbers, quoted per property after a site visit.
PVGIS (the EU's peer-reviewed solar model) puts Thanet at around 950-1,020 kWh per installed kWp per year for a south-facing 30-40 degree roof. That's about 10% higher than the England average because Thanet is one of the sunniest districts in the UK - typically 1,650-1,780 sunshine hours per year vs 1,400 nationally. A 4kW system on a south-facing Palm Bay roof will produce around 3,900-4,000 kWh a year. East/west split roofs come in about 15% lower. North-facing single-slope: I'll usually steer you away.
Solar and battery is quoted per property after a site visit. Panel type, roof pitch, orientation, existing consumer unit, battery size, DNO capacity and any conservation-area or heritage work all move the number, and a real quote reflects the actual system that will be installed. VAT on domestic solar and battery is currently zero-rated to 31 March 2027 under the Energy-Saving Materials scheme; the quote reflects that.
I'll do a proper individual quote based on your actual usage from your last four bills, not a glossy sales-pitch payback figure.
UK Power Networks (the DNO for Margate) split solar/battery notifications at 3.68kW inverter output per phase. Systems at or below that are G98 - install first, notify within 28 days. Systems above are G99 - pre-installation approval required, and UKPN can take 4-11 weeks to respond. Most modern PV installs push past 3.68kW because a 4kW hybrid inverter is common. I submit G99 applications at survey stage so approval usually lands by the time we're ready to install. Rare "constrained network" cases in older Cliftonville mansion blocks may need a service upgrade first.
SEG rates vary wildly by supplier. As of 2026 the top rates for domestic customers are Octopus Outgoing Fixed (15p/kWh), followed by E.ON Next Export (12.5p) and Scottish Power (12p). Some suppliers still offer 3-5p flat - not worth switching to for the export tariff alone, but if you're already with Octopus for import their Go tariff + Outgoing Fixed export combination is currently the best deal. I don't take referral fees from any supplier.
Roof survey: 45 minutes. G99 DNO application: 4-11 weeks parallel to prep. Install: 2 days for standard 4kW PV, 3 days with battery. G98 sign-off: same day. MCS certificate: 2-4 weeks after install. First SEG payment: 6-8 weeks depending on supplier meter registration.
I won't oversize a system to the point the SEG payback is longer than the install age. I won't recommend battery to a household that's on a flat-rate tariff and away 6 hours a day - the payback doesn't stack. And I won't install on a roof that needs a re-slate in 3 years - we do the roof first or wait.
Always on every job